The next few weeks of work, and what changed since the last update.
What it does
The look-ahead lists every activity starting, finishing or in progress in the 2, 3, 4 or 6 weeks after the data date, filtered by WBS, activity code or critical and near-critical work. The period report sets an update against the one before it: what started, finished and slipped, how milestones moved, which activities joined or left the critical path, percent complete, and SPI, BEI and CPLI.
A Gantt with bars coloured by float; the critical chain stands out.
What it helps you achieve
Hand site teams a short, filtered list of the work coming up.
Write the monthly update narrative from facts rather than memory.
Spot slipping work and milestone movement as soon as an update arrives.
How to run it
Where to find it: A schedule update's page → Look-ahead or Period report
Open a schedule update from the project page.
Choose Look-ahead, pick the window and any filters, then Update.
Or choose Period report: it compares with the update just before this one, and you can pick another.
Download either report as Excel or PDF.
What you get
A look-ahead table with start, finish, remaining duration and float.
Started, finished and slipped lists, milestone movement and critical path changes for the period.
Percent complete and SPI, BEI and CPLI, each with the reason when it can't be worked out.
Excel and PDF downloads of both reports.
Good to know
Near-critical means 5 days of total float or less, the same as everywhere else in the app.
Activities are matched between updates by Activity ID.
Limits, stated plainly
SPI needs earned value from P6 financial periods; most exports don't carry it, so it shows N/A with the reason.
BEI and CPLI need a baseline of the same kind of file set on the project.
Try Look-ahead and period reports on your own schedules. ScheduleReport is invite-only while we’re in early access.