Schedule recalculation engine

Recalculate a schedule from its own logic, calendars and progress.

What it does

A built-in critical path engine. It walks the schedule's relationships forwards and backwards using each activity's work calendar (including shifts, lunch breaks and holidays), retained-logic progress handling and constraints, and produces early and late dates, total float and the critical path. It is what makes Time Impact Analysis and Collapsed As-Built possible, because both need a schedule recalculated under a hypothetical.

StartActivityActivityFinishForward pass: earliest start / finishBackward pass: latest start / finish, floatusing each activity’s own calendar, shifts and holidays
A forward pass sets earliest dates; a backward pass sets latest dates and float.

What it helps you achieve

  • Answer 'what if' questions on a real schedule without opening P6.
  • Get delay results that come from recalculation, not from guessing at knock-on effects.

How to run it

Where to find it: Runs behind Time Impact Analysis and Collapsed As-Built

  1. There is nothing to configure: it runs automatically whenever you run a Time Impact Analysis or a Collapsed As-Built analysis.

What you get

  • Dates and float that respect each activity's own calendar, shifts and holidays.
  • Out-of-sequence progress handled the way P6's retained logic handles it.

Good to know

  • It has been checked against real Primavera P6 exports: on the schedules used to validate it, its late dates and total float matched P6's own stored values on every comparable activity, and its early dates matched on all but a handful (well under one percent).
  • For P6 XML, Microsoft Project and Asta files it checks itself on each file: it recalculates the file and compares early start, early finish and total float with the file's own values. The delay analyses turn on for that file only when at least 98% agree on each; the file's page says which way it went and why.

Limits, stated plainly

  • Schedules that use P6's Progress Override setting are not supported yet, and the analysis says so instead of guessing.
  • It reproduces P6's calculation; where a file gives it something ambiguous, the analysis reports the limit rather than smoothing it over.

Try Schedule recalculation engine on your own schedules. ScheduleReport is invite-only while we’re in early access.

Request access

Frequently asked questions

Does it replace Primavera P6?
No. It reads P6 exports and recalculates them for analysis. You keep scheduling in P6.