DCMA-14 · Check 5 of 14
Hard constraints
Incomplete tasks with a Mandatory Start or Mandatory Finish constraint.
Threshold< 5%
What it measures
How many unfinished tasks are pinned to a date instead of being driven by the logic.
How ScheduleReport calculates it
Counts incomplete tasks that carry a Mandatory Start or Mandatory Finish constraint, checking both the primary and secondary constraint where an activity has both, divided by the incomplete tasks evaluated. The check passes below 5%.
Why it matters
A hard constraint overrides the network. The date it forces is what the schedule shows, whatever the logic would have produced, which can hide float or delay.
How to fix a failure
- Remove the constraint and let the logic drive the date, or replace it with a soft constraint such as Start No Earlier Than where a real external date exists.
- Where a mandatory date is contractual, document it and keep it on a milestone rather than on working activities.
ScheduleReport runs all 14 checks on any schedule you upload, and lists the exact activities behind every failure. See how the health check works.